Andrew Corporation - USA
Designed and supplied 64 x 3.7m dish heater panels designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.

Thursday, 23 February 2006

Drayton House - Drayton
Designed and supplied the materials for a large scale water leak detection system.

Wednesday, 22 February 2006

Huby Water Treatment Works
Supplied and installed frost protection to the external PVC pipework.

Tuesday, 21 February 2006

Direct Table Foods - Suffolk


For this large project, ESH supplied and installed 1150m of WinterTrace constant wattage heating cable to frost protect the sprinkler systems in the cold storage rooms.

Tuesday, 14 February 2006

Caterpillar UK - Larne 
Designed and supplied 20 battery heater pads 1050mm x 200mm C/W with a 3000mm cold lead.

Friday, 3 February 2006

Kraft Foods UK Ltd (now Monedelez International)
Now Europe's largest chocolatier and biscuit maker and second largest maker of candy and coffee, ESH's project was part of their 'Coffee Operation'. Here we supplied and installed Trace Heating for frost protection to the cold water pipework and also the temperature maintenance of the plastic caustic pipework.

Thursday, 2 February 2006

Dungeness Nuclear Power Station
Supplied 150m of FBTBOJ10/1 to this industrial project.