Hopping Hill Primary School - Northampton
ESH supplied and installed 100m of ESRSBOJ trace heating tape to maintain +5°C on the domestic cold water pipework.
CPS Fuels LTD - Cambridgeshire
The project scope was to supply and install trace heating tape, insulation and cladding in order to maintain the pipework at +15°C. The 3" bio diesel pipework was in a Zone 1 Gas Group 11B Hazourdous Area.
Police Station - Leamington Spa
Supplied 240m of VC8/2 constant wattage heating tape to perform the duty of frost protecting the chilled water pipework.
11 Tudor Hill - Sutton Coldfield
ESH supplied, installed and commissioned the trace heating system to maintain the ceiling void DHWS pipework at 65°C and also to frost protect a 15mm pipe in the stores area.
John Bull Confectioners - Bridlington
Supplied 85m of FBT40/2 to maintain a pipe line between 60°C - 70°C.
Sunrise Senior Living - Solihull
Supplied tools, materials and labour to install and commission the frost protection trace heating system for VT and CT heating, chilled water, BCWS and BHWS services. 242m of type VC constant wattage heating tape was required.
Sunrise Senior Living - Cardiff
Supply and installed a frost protection trace heating system for the heating, chilled water and mains cold water pipework in two areas, plus a 2m hose point pipe.
Lady Elizabeth Hastings Church Of England School - Leeds
Supplied and installed H2OWAT55 self regulating heating tape to temperature maintain the hot water pipework at 55°C.
Jemstock - London
Supplied and installed trace heating to frost protect the water mains from Discovery Dock to the Jemstock project.
Oldham Community College
100m OF H2OWAT65 was supplied and installed to maintain the DHWS at 55°C together with accessories to purge the system weekly to sterilize & prevent the formation to Legionella.
Abbey Primary School - Northampton
ESH supplied and installed trace heating to provide the frost protection on the BCWS, DHWS F+R and HTG F+R circuits. This required 750m of ESRSBOJ self limiting tape. We also supplied the labour to remove the existing trace heating, insulation & cladding from skid units and re-install as much as possible the insulation & cladding only replacing with new where required.
Lea And Perrins - Worcester
Back to Lea And Perrins, this time to supply and install thermal insulation to the ground floor condensate pipework.
Mikrokom Slovenskp Sro - Slovakia
Designed and supplied 8 x 4.6M dish heater panels designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.
Lea And Perrins - Worcester
Supplied and installed the thermal insulation for the Worcester Sauce, Water and Steam pipework.