Manchester Joint Hospitals
ESH supplied and installed trace heating for both frost protection and hot water temperature maintenance. In total 573m of constant wattage heating tape and 150m of self regulating tape was installed.
Newhall School - Sutton Coldfield
Provided frost protection to the roof pipework. In total we supplied and installed just over 100m of VC12/2 constant wattage heating tape.
Opus 9 - Wednesbury
For this project we supplied and installed trace heating tape to provide frost protection to the roof pipework.
Huntstown Waste Water Treatment Plant
ESH supplied and installed trace heating to a number of different vessel delivery points, including the sodium bisulphate, caustic soda, service water supply, waste transfer and aeration pipework.
North Trafford College - Manchester
Supplied materials and labour to install and commission the trace heating system to provide frost protection to the chilled water pipework within this modern further education college.